Hi,
Trying to understand a case study in relation to it’s ASE performance, I see that the default schedule runs from 9 am to 5 pm on weekdays.
I’ve found that the default schedule for the AnnualDaylight
recipe runs from 8 am to 5 pm (see here).
Saying so, the LEED requirement for schedule says that it should be 10 hours going from 8 am to 6 pm all days (3650 hours in total), as the IES-LM-83-12 demands:
Just want to be sure if the ASE component uses the LEED requirements or the default schedule. If the later, i guess this should be revised in order to comply to LEED (and hopefully it is not messing with the schedule used for the AnnualDaylight
calculation).
BTW, i think the requirements for LEED sDA are the same as the ASE’s. Worthwhile to check.
@mikkel, any thoughts from you?
Thanks,
-A.